FS Agreement No. 08-MU-11030510-010
MODIFICATION NO. 04
to
AGREEMENT NO. 08-MU-11030510-010
between
USDA fOREST SERVICE,
CORONADO NATIONAL FOREST
and
ROSEMONT COPPER COMPANY
This modification is issued pursuant to Clause No. F. 15 and Attactment 2.
Attachment 2 of the MOU is replaced with the attached revised timeline.
Except as provided herein, all terms and conditions of the referenced document remain unchanged and in full force.
| Rosemont Copper Company | USDA Forest Service | ||
| 11/14/09 | 11/19/09 | ||
| GIL CLAUSEN | Date | JEANINE A. DERBY | Date |
| President and CEO | Forest Supervisor | ||
| The authority and format of this instrument has been reviewed and approved for signature: | |||
| 11/19/09 | |||
| NORENE NORRIS | DATE | ||
| Grants & Agreements Specialist | |||
ATTACHMENT 2
EIS Timeline
Rosemont Copper Project
Notes:
| Task | 2010 Accomplishment |
| Internal review of DEIS. | 1st quarter (January - March) |
| Publish Notice of Abailabliity and 90-day comment period in Federal Register. | April 2010 |
| Hold public meetings, hearings, and accept public comments | 2nd quarter (April - June) |
| Comment analysis, FEIS supplemented or revised to incorporate comments. Internal review completed. | 3rd quarter (July-September) |
| ROD issued. | 4th quarter (October - December) |
Original Subject to Modification as Detailed Above:
| Milestone | Date |
| Scoping Reports | July 2009 |
| Draft Environmental Impact Statement (DEIS) | November 2009 |
| 90-Day DEIS Public Comment Period | November 2009 to February 2010 |
| Final Environmental Impact Statement (FEIS) | July 2010 |
| Record of Decision (ROD) | July 2010 |